Schedule

Schedule

The design phase of the project started in 2019 and will continue through 2021. Community members will have an opportunity to provide input through both in-person and online open houses during design and environmental review throughout 2020. Construction is scheduled to begin in 2022 and to be complete in 2023 before the new light trail station opens.

Feasibility Study
2017

Completed

Design/Environmental Review
2019–2021

Right-of-Way
2021–2022

Construction
2022–2023

Alternative Evaluation

September 2019​–​June 2020

December​–​March

Property owner briefings

Community briefings and presentations

April

Online open house, survey, and presentation

Preferred Alternative Selection

Summer 2020

Property owner briefings

Community briefings and presentations

Online and in-person open house

30% Design Completion

Summer​/​Fall 2020

Property owner briefings

Possible community briefings and presentations

Possible online and in-person open house

Research and Planning

In 2016 and 2017, the City of Shoreline did a study to evaluate and recommend options for linking the communities on the west side of I-5 to the future Sound Transit Shoreline South/145th Station. City of Shoreline staff, Shoreline City Council, and consulting engineers evaluated five options. Public comment was provided at Shoreline City Council meetings.

The City estimated the location at N 148th Street would cost the least to construct, likely draw the most users, and of the routes possible, provide the shortest and most direct access to the Shoreline South/145th Station. The City also reviewed WSDOT and Sound Transit regulations in order to address safety needs around and across I-5. Shoreline City Council approved this location in February 2017.